Because of low efficiency in production process and numerous problems in previous power and control system that was done by a foreign contractor and machinery manufacturing company, the project was done with complete change in monitoring and control system and doing fundamental reforms in main and local panels in a four months period, so that the employer expressed much satisfaction with the project. The capabilities added to the project, in addition to full control over production line, includes:
Redundancy in monitoring servers, full reporting of the total raw materials and weekly and monthly production, pellet and mill current curves, precise weighting using Siemens Siwarex hardware, and recording and displaying the alarms.
YEAR : 2014
PLC:S7-300
CPU: 317-2PN/DP
SCADA: WINCC
2 STATION SERVER & 3 STATION CLIENT
HMI: KTP 1000
NETWORK : ETHERNET,MODBUS,PROFIBUS
DRIVE: MICRO MASTER 420,430,440